Ambiguous Plan Provisions Would Not Be Interpreted To Deny Potential Administrative Claimant Its Right To Payment In Full
Forklift LP Corp. v. iS3C, Inc. (In Re Forklift LP Corp.), 363 B.R. 388 (Bankr. D. Del. 2007) (Judge Peter J. Walsh)
In connection with pending litigation over a failed post-petition software upgrade, the plaintiff asserted that even if its challenge to defendant’s right to payment was unsuccessful, the defendant’s administrative claim was subject to the provisions of the confirmed Plan, which, the plaintiff contended, resulted in defendant receiving less than full payment. Defendant moved for partial summary judgment on its right to receive payment in full, arguing that the Plan was ambiguous. The Court agreed, and held that the ambiguity in the Plan would not deny defendant its right to payment in full in light of the clear language of the Confirmation Order, the Disclosure Statement and the doctrine of judicial estoppel.
Continue Reading...